When you get a solar battery, you need to inform the energy distributor in your area so they can manage the energy coming in and out of the grid (similar to when you installed your solar system).
While it’s called something different in each state, it’s a routine process that usually takes around two weeks depending on which distribution zone you’re in. In Queensland, it can take up to 65 business days.
In the unlikely event that the distributor has further questions about your application, we’ll let you know so you can handle it directly.
In the very unlikely event the distributor doesn’t approve your application we’ll refund your $250 deposit, no questions asked.